Okay - Going on vacation for a week starting tomorrow. When I return my plans are to be done with this crap by the end of FEB next year.
1.Add a high flow cat--------By NOV 30
2.Add a E-Fan---------------By DEC 14
3.Add under drive pulley's-----BY DEC 28
4.Coil------------------------BY JAN 11
5.Dyno tune and produce some numbers!----BY JAN 25---1st chart
6.Add headers------------------------------BY FEB 8
7.Dyno tune and produce some numbers!-----BY END OF FEB--2nd chart--Hopefully a baseline for the next step.
Now, hold me to these dates. If I don't have something done by the dates I've listed then either something major happened or my wife thru a fit.
Okay, Step 2 Is done. Step 3 will be done around DEC 8. I'm skipping the high flow cat for now...
Just might be done sooner than I thought. Starting to get a little cooperation from the other half...